4th & Oates Storm Water Improvements Project - Update

Storm Lake Jump Right In



For Immediate Release: 04/7/2020

For more information contact:           


Keri Navratil

712-732-8000

Navratil@stormlake.org


The 4th & Oates Storm Water Improvements Project will begin on April 13, 2020.  Traffic patterns will be affected and traffic control measures by the contractor will be in place.  Following are the noted changes for the next month:


Phase 1: Oates Street between East 5th Street and East 4th Street – Partial Lane Closure.

Duration: 1 Week.

Pavement Removals: April 15th through April 17th.

Storm Sewer: April 20th through April 27th.

Street Paving: April 29th through May 1st.


Phase 2: North end of Oates Street at East 5th Street – Full Road Closure.

Duration: 4 Days.

Pavement Removals: Under Phase 1.

Storm Sewer: April 28th through May 1st.

Street Paving: April 29th through May 1st.


Questions can be directed to the City of Storm Lake at telephone number 712-732-8000.